Meeting Date: 11/15/2016
Preview
The Board will hear a request from the Department of Public Works to authorize budget adjustments related to the Civic Center Drive Improvement Project in San Rafael. Public Works is requesting that the Department of Finance be allowed to make budget adjustments to fun an additional contingency for the project, which is underway and expected to be completed in early 2017.
Review
The Board authorized the budget adjustments related to the Civic Center Drive Improvement Project.
Need more info? See the staff report about the construction contingency for the Civic Center Drive Improvement Project.
Contact: Patrick Zuroske, Facilities Planning & Development Manager, Department of Public Works